Date Range Page of the Recalc Wizard
Use this page to select the date range that you want to use in recalculating costs.
Date Range
Field | Description | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
Recalc all periods in your project | Select this option to recalculate costs for the entire project — from project start to project end. When you select this option, the recalculation process allows the change of historical data. | ||||||||||
Recalc all periods after the current period | Select this option to recalculate costs for only those periods remaining after the status date. When you select this option, the recalculation process does not affect historical data. | ||||||||||
Recalc costs in a specific date range | Select this option to recalculate costs for a specific date range.
Use the
From and
To fields to enter or select the start and end dates of the date range.
Cobra displays an error if the date in the To field is earlier than the date in the From field. If both dates in the From and To fields are the first period in the calendar, both the start and end dates are the first dates in the calendar. Note: The Date Lookup dialog box displays the calendar period labels for calendar set 00.
For a better understanding of the many ways date ranges are used, refer to the sample project data and table below. Sample Project Data
|
Click Next to go to the Confirmation page, or click Finish to start recalculating costs.